• Project Name: 3,816 Sq Ft, Warehouse
  • Client: Boskovich farms
  • Location: California
  • Year Completed::
  • Architect::

The project includes the installation of refrigeration panels around the A/C ducts, installation of ceiling panels supported by a truss, and A/C grill cutouts according to airflow requirements. We also installed 576 sq ft of refrigeration panels on 16 ft high walls including trim.

The project also included the installation of 36 x 48 ft Double Acting traffic doors with guards. Saw cutting concrete and excavating 4 feet to install floor drains with a 24×24 in drain opening.

 Prep Room 

To Include the following: A. Install 4″ Refrigeration panels ( Approx 3,824) 1. Install 4″ White Refrigeration panels in areas according to plans ( 16′ high) 2. Install Trim pieces, silicone, butyl, screws and foam

  1. Epoxy Flooring ( approx 76′ x 29′) 1. Grind and Prep area 2. Torch area for sanitation 3. Apply Epoxy fastop 12s & paint
  2. Relocate existing bumper door and install in another area 1. uninstall existing door and install in new area Labor only, We are reusing old door
  3. Install 2 qty – 12″ x 12″ floor drain 1. Saw cut concrete 2. Excavate 4′ deep 3. Install floor drains 4. Cover drain with dirt and compact properly

Install 2 drains in the Herb Room and level the floor to pitch towards the drains

To Include the following: A. Saw cut concrete B. Excavate 4′ deep C. Install floor drains D. Cover drain with dirt and compact properly E. Level floor and pitch towards the drain 

Outside Expansion

To Include the following: A. Install 4″ Refrigeration panels (2,752 sq ft) 1. Install 4″ White Refrigeration panels in areas according to plans ( 16′ high) 2. Install Trim pieces, silicone, butyl, screws and foam

  1. Install Ceiling Panels (Area 46′ x 40′) 1. Install 4″ White Refrigeration Ceiling panels 2. Install t-bar 3. Install Trim pieces, silicone, butyl, screws and foam
  2. Epoxy Flooring ( approx 46′ x 40′) 1. Grind and Prep area 2. Torch area for sanitation 3. Apply Epoxy fastop 12s & paint
  3. Fill in Channel on the top of dock with concrete & level 2″ wide Area sizes 36′ LFT & 20′ LFT A. Fill in with cement and level
  4. Install 3 qty – 12″ x 12″ floor drain 1. Saw cut concrete 2. Excavate 4′ deep 3. Install floor drains 4. Cover drain with dirt and compact properly
  5. Demo one Ramp 1. Break concrete, remove the dirt and level haul away debris
  6. Relocate Sump pump pit by 5 feet 1. Saw cut area where new pit where be located (6′ x 6′ area) 2. Excavate 7′ deep 3. frame it with plywood 2′ x 4′ 4. Reconnect pipes 5. Install Grate ( use grate from old pit area) 6. Back fill old pit area and compact with dirt and cement
  7. Raise the foundation 3′ high (area 28’x 36′ ) A. Frame area to prep for concrete B. Dial in Rebar 5/8 C. Back fill with dirt D. Pour Cement E. Remove the ramp by saw cutting in to pieces. Haul away debris

Install Epoxy Flooring – Full Hallway 

To Include the following:

Area: 11′ x 114′

  1. Grind and Prep area
  2. Torch area for sanitation
  3. Apply Epoxy #46 White Aluminum Oxide